Performance of Corrective Work Does Not Extend the Deadline to File Mechanics’ Lien Claims in Pennsylvania
Mechanics’ liens are powerful remedies for contractors involved in payment disputes with owners of construction projects in Pennsylvania, but the six month deadline under the Mechanics’ Lien Law is strictly construed and contractors who delay filing them may lose their rights. In Neelu Enterprises, Inc. v. Agarwal, the Pennsylvania Superior Court considered the deadline for a contractor to file lien claims “within six months after the completion of his work” set forth in Section 502 of the Pennsylvania’s Mechanics’ Lien Law. Specifically, the two issues in the case were whether the deadline begins to run after a contractor is terminated and whether the deadline can be extended by the subsequent performance of corrective or remedial work.